Process Engineering
Terminology
(what process Engineers say and what they mean by it)
- Major Technological Breakthrough
-> Back to the drawing board.
- Developed after years of
intensive research
-> It was discovered by accident.
- Project slightly behind original
schedule due to unforeseen difficulties
-> We are working on something else.
- The designs are well within
allowable limits
-> We just made it, stretching a point or two.
- Customer satisfaction is believed
assured
-> We are so far behind schedule that the customer was happy
to get anything at all.
- Close project co-ordination
-> We should have asked someone else; or, let's spread the
responsibility for this.
- The design will be finalised in
the next reporting period
-> We haven't started this job yet, but we've got to say
something.
- A number of different approaches
are being tried
-> We don't know where we're going, but we're moving.
- Test results were extremely
gratifying
-> It works, and are we surprised!
- Extensive effort is being applied
on a fresh approach to the problem
-> We just hired three new guys; we'll let them kick it
around for a while.
- Preliminary operational tests are
inconclusive
-> The darn thing blew up when we threw the switch.
- The entire concept will have to
be abandoned
-> The only guy who understood the thing quit.
- Modifications are underway to
correct certain minor difficulties
-> We threw the whole thing out and are starting from
scratch.
- Essentially complete
-> Half done.
- We predict...
-> We hope to God!
- Drawing release is lagging.
-> Not a single drawing exists.
- Risk is high, but
acceptable.
-> 100 to 1 odds, or with 10 times the budget and 10 times
the manpower, we may have a 50/50 chance.
- Serious, but not insurmountable,
problems.
-> It will take a miracle. God should be the program
manager.
- Not well defined.
-> Nobody's thought about it.
- Requires further analysis and
management attention.
-> Totally out of control.
Back to Joke List
|